The next step on the barn (other wise known as the Cabarn) is to enclose the sleeping area. Kevin came down from SLC and helped me hand dig footings, install a layer of visqueen (plastic), leveled the base, installed #4 rebar in the footings and a #3 rebar mat.
Under slab plumbing for the bathroom and kitchenette.
Brian came up form St. George and helped me pour the slab.